Roads & HighwaysIPM · Central Project#618884

Construction of Four Lane Highway from Ghazipur- Ballia-UP/Bihar State Border Greenfield section of NH-31 Package II [from Shahapur km 42.500 to Pindari km 78.150] on EPC Mode in the state of Uttar Pradesh.

Ministry of Road Transport & HighwaysUttar Pradesh
Revised Cost: ₹1311 CrUtilization: 60.3%

Original Cost

₹1494 Cr

Baseline estimate

On budget

Revised Cost

₹1311 Cr

Latest approved cost

Expenditure

₹790 Cr

Spent to date

Utilization

60.3%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹521 Cr

Budget left

Budget Utilization

60.3%
0%25%50%75%100%

Spent

₹790 Cr

Remaining

₹521 Cr

Total

₹1311 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

26/10/2025

Revised Completion

30/09/2026

Completed

Project Details

Project Code618884
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateUttar Pradesh
Data Month2026-08

Financial Summary

Original Cost₹1494 Cr
Revised Cost₹1311 Cr
Expenditure₹790 Cr
Original End Date26/10/2025
Revised Date30/09/2026

Project Intelligence

Project is within original budget of ₹1494 Cr — no cost escalation recorded.

Expenditure stands at ₹790 Cr, which is 60.3% of the revised project cost.

Remaining budget: ₹521 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of Four Lane Highway from Ghazipur- Ballia-UP/Bihar State Border Greenfield section of NH-31 Package II [from Shahapur km 42.500 to Pindari km 78.150] on EPC Mode in the state of Uttar Pradesh. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1494.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of Four Lane Highway from Ghazipur- Ballia-UP/Bihar State Border Gr"?
Construction of Four Lane Highway from Ghazipur- Ballia-UP/Bihar State Border Greenfield section of NH-31 Package II [from Shahapur km 42.500 to Pindari km 78.150] on EPC Mode in the state of Uttar Pradesh. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹1494 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1494 Cr and has been revised to ₹1311 Cr — a cost overrun of -12.2%. Expenditure to date: ₹790 Cr (60.3% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of Four Lane Highway from Ghazipur- Ballia-UP/B is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618884. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Four Lane Highway from Ghazipur- Ballia-UP/B is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.