Original Cost
₹1706 Cr
Baseline estimate
Revised Cost
₹1580 Cr
Latest approved cost
Expenditure
₹799 Cr
Spent to date
Utilization
50.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹781 Cr
Budget left
Spent
₹799 Cr
Remaining
₹781 Cr
Total
₹1580 Cr
Project Approved
Construction / Implementation
Original End Date
02/07/2025
Revised Completion
30/04/2026
Completed
Project is within original budget of ₹1706 Cr — no cost escalation recorded.
Expenditure stands at ₹799 Cr, which is 50.6% of the revised project cost.
Remaining budget: ₹781 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.