Construction of four-lane elevated viaduct from km.4634 to km.6345 on NH-24A including Retaining wall, service lane, at grade road and improvement of junctions, on EPC mode
Original Cost
₹185 Cr
Baseline estimate
Revised Cost
₹270 Cr
Latest approved cost
Expenditure
₹175 Cr
Spent to date
Utilization
64.9%
Of revised budget
Cost Status
+45.8%
+₹85 Cr increase
Remaining
₹95 Cr
Budget left
Budget Utilization
64.9%Spent
₹175 Cr
Remaining
₹95 Cr
Total
₹270 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹185 Cr
Revised Cost
₹270 Cr
Increase
+₹85 Cr
Escalation
+45.8%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
27/09/2023
Revised Completion
31/12/2024
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹85 Cr (45.8%) from the original estimate of ₹185 Cr.
Expenditure stands at ₹175 Cr, which is 64.9% of the revised project cost.
Remaining budget: ₹95 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of four-lane elevated viaduct from km.4634 to km.6345 on NH-24A including Retaining wall, service lane, at grade road and improvement of junctions, on EPC mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹185.00 Cr, later revised to ₹269.81 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of four-lane elevated viaduct from km.4634 to km.6345 on NH-24A inc"?
- Construction of four-lane elevated viaduct from km.4634 to km.6345 on NH-24A including Retaining wall, service lane, at grade road and improvement of junctions, on EPC mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹185 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹185 Cr and has been revised to ₹270 Cr — a cost overrun of +45.8%. Expenditure to date: ₹175 Cr (64.9% of revised cost). Data as of 2026-05.
- QWhich ministry is responsible for this project?
- Construction of four-lane elevated viaduct from km.4634 to k is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618008. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of four-lane elevated viaduct from km.4634 to k is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.