Construction of flyover at Gammon Junction at Km.903.265 on NH16 including vent at Diwancheruvu junction at Km.902.308 Blackspot ID No.AP03299 in Andhra Pradesh on EPC mode under NHO
Original Cost
₹327 Cr
Baseline estimate
Revised Cost
₹223 Cr
Latest approved cost
Expenditure
₹61 Cr
Spent to date
Utilization
27.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹163 Cr
Budget left
Budget Utilization
27.2%Spent
₹61 Cr
Remaining
₹163 Cr
Total
₹223 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
20/10/2027
Revised Completion
20/10/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹327 Cr — no cost escalation recorded.
Expenditure stands at ₹61 Cr, which is 27.2% of the revised project cost.
Remaining budget: ₹163 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of flyover at Gammon Junction at Km.903.265 on NH16 including vent at Diwancheruvu junction at Km.902.308 Blackspot ID No.AP03299 in Andhra Pradesh on EPC mode under NHO is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹327.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of flyover at Gammon Junction at Km.903.265 on NH16 including vent "?
- Construction of flyover at Gammon Junction at Km.903.265 on NH16 including vent at Diwancheruvu junction at Km.902.308 Blackspot ID No.AP03299 in Andhra Pradesh on EPC mode under NHO is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andhra Pradesh. Original cost: ₹327 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹327 Cr and has been revised to ₹223 Cr — a cost overrun of -31.7%. Expenditure to date: ₹61 Cr (27.2% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of flyover at Gammon Junction at Km.903.265 on is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618525. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of flyover at Gammon Junction at Km.903.265 on is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.