Roads & HighwaysIPM · Central Project#619004

Construction of Dubrajpur Bypass with 4-lane configuration of length 5.676 km on NH-60 new NH-14 from design chainage 0.00 existing km 316.135 on NH-60 to design chainage 5.676 existing km 320.980 on NH-60 in the district of Birbhum, West Bengal under Annual Plan 2022-23 in EPC Mode- reg. Job. No. 014-WB-2022-23/518 .

Ministry of Road Transport & HighwaysWest Bengal
Revised Cost: ₹561 CrUtilization: 27.7%

Original Cost

₹561 Cr

Baseline estimate

On budget

Revised Cost

₹561 Cr

Latest approved cost

Expenditure

₹156 Cr

Spent to date

Utilization

27.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹405 Cr

Budget left

Budget Utilization

27.7%
0%25%50%75%100%

Spent

₹156 Cr

Remaining

₹405 Cr

Total

₹561 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

18/12/2027

Revised Completion

17/12/2027

Completed

Project Details

Project Code619004
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateWest Bengal
Data Month2026-08

Financial Summary

Original Cost₹561 Cr
Revised Cost₹561 Cr
Expenditure₹156 Cr
Original End Date18/12/2027
Revised Date17/12/2027

Project Intelligence

Project is within original budget of ₹561 Cr — no cost escalation recorded.

Expenditure stands at ₹156 Cr, which is 27.7% of the revised project cost.

Remaining budget: ₹405 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of Dubrajpur Bypass with 4-lane configuration of length 5.676 km on NH-60 new NH-14 from design chainage 0.00 existing km 316.135 on NH-60 to design chainage 5.676 existing km 320.980 on NH-60 in the district of Birbhum, West Bengal under Annual Plan 2022-23 in EPC Mode- reg. Job. No. 014-WB-2022-23/518 . is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹561.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of Dubrajpur Bypass with 4-lane configuration of length 5.676 km on"?
Construction of Dubrajpur Bypass with 4-lane configuration of length 5.676 km on NH-60 new NH-14 from design chainage 0.00 existing km 316.135 on NH-60 to design chainage 5.676 existing km 320.980 on NH-60 in the district of Birbhum, West Bengal under Annual Plan 2022-23 in EPC Mode- reg. Job. No. 014-WB-2022-23/518 . is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: West Bengal. Original cost: ₹561 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹561 Cr has not been significantly revised. Expenditure: ₹156 Cr (27.7% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of Dubrajpur Bypass with 4-lane configuration o is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619004. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Dubrajpur Bypass with 4-lane configuration o is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.