Original Cost
₹300 Cr
Baseline estimate
Revised Cost
₹300 Cr
Latest approved cost
Expenditure
₹82 Cr
Spent to date
Utilization
27.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹218 Cr
Budget left
Spent
₹82 Cr
Remaining
₹218 Cr
Total
₹300 Cr
Project Approved
Construction / Implementation
Original End Date
30/04/2025
Revised Completion
31/03/2026
Completed
Project is within original budget of ₹300 Cr — no cost escalation recorded.
Expenditure stands at ₹82 Cr, which is 27.4% of the revised project cost.
Remaining budget: ₹218 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.