Construction of Bypass on NH-59 from Km 336/350 to 349/910 13.56 km near Berhampur town including 4-lane RoB in the state of Odisha.

Ministry of Road Transport & HighwaysOdisha
Revised Cost: ₹197 CrUtilization: 47.1%

Original Cost

₹197 Cr

Baseline estimate

On budget

Revised Cost

₹197 Cr

Latest approved cost

Expenditure

₹93 Cr

Spent to date

Utilization

47.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹104 Cr

Budget left

Budget Utilization

47.1%
0%25%50%75%100%

Spent

₹93 Cr

Remaining

₹104 Cr

Total

₹197 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

11/12/2025

Revised Completion

31/12/2026

Completed

Project Details

Project Code617930
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateOdisha
Data Month2026-08

Financial Summary

Original Cost₹197 Cr
Revised Cost₹197 Cr
Expenditure₹93 Cr
Original End Date11/12/2025
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹197 Cr — no cost escalation recorded.

Expenditure stands at ₹93 Cr, which is 47.1% of the revised project cost.

Remaining budget: ₹104 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of Bypass on NH-59 from Km 336/350 to 349/910 13.56 km near Berhampur town including 4-lane RoB in the state of Odisha. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹197.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of Bypass on NH-59 from Km 336/350 to 349/910 13.56 km near Berhamp"?
Construction of Bypass on NH-59 from Km 336/350 to 349/910 13.56 km near Berhampur town including 4-lane RoB in the state of Odisha. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹197 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹197 Cr has not been significantly revised. Expenditure: ₹93 Cr (47.1% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of Bypass on NH-59 from Km 336/350 to 349/910 1 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617930. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Bypass on NH-59 from Km 336/350 to 349/910 1 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.