Original Cost
₹1209 Cr
Baseline estimate
Revised Cost
₹1182 Cr
Latest approved cost
Expenditure
₹502 Cr
Spent to date
Utilization
42.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹680 Cr
Budget left
Spent
₹502 Cr
Remaining
₹680 Cr
Total
₹1182 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2027
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹1209 Cr — no cost escalation recorded.
Expenditure stands at ₹502 Cr, which is 42.5% of the revised project cost.
Remaining budget: ₹680 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.