Construction of Balrampur bypass with 2L flexible pavement configuration from km.223.000 of NH-330 to km.328.300 of NH-730 under EPC mode
Original Cost
₹516 Cr
Baseline estimate
Revised Cost
₹516 Cr
Latest approved cost
Expenditure
₹365 Cr
Spent to date
Utilization
70.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹151 Cr
Budget left
Budget Utilization
70.8%Spent
₹365 Cr
Remaining
₹151 Cr
Total
₹516 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
02/02/2026
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹516 Cr — no cost escalation recorded.
Expenditure stands at ₹365 Cr, which is 70.8% of the revised project cost.
Remaining budget: ₹151 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of Balrampur bypass with 2L flexible pavement configuration from km.223.000 of NH-330 to km.328.300 of NH-730 under EPC mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹516.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of Balrampur bypass with 2L flexible pavement configuration from km"?
- Construction of Balrampur bypass with 2L flexible pavement configuration from km.223.000 of NH-330 to km.328.300 of NH-730 under EPC mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹516 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹516 Cr has not been significantly revised. Expenditure: ₹365 Cr (70.8% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of Balrampur bypass with 2L flexible pavement c is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618054. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Balrampur bypass with 2L flexible pavement c is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.