Construction of Balance Work of the 4-Laning of the Section from Jorhat to Jhanji of NH-37 Old from Km 453.000 to Km 490.800, under SARDP- NE , under EPC Mode in the state of Assam Pkg-IV Structures & Toll Plaza
Original Cost
₹279 Cr
Baseline estimate
Revised Cost
₹279 Cr
Latest approved cost
Expenditure
₹399 Cr
Spent to date
Utilization
142.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹0 Cr
Budget left
Budget Utilization
142.8%Spent
₹399 Cr
Remaining
₹0 Cr
Total
₹279 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
11/08/2024
Revised Completion
31/07/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹279 Cr — no cost escalation recorded.
Expenditure stands at ₹399 Cr, which is 142.8% of the revised project cost.
Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of Balance Work of the 4-Laning of the Section from Jorhat to Jhanji of NH-37 Old from Km 453.000 to Km 490.800, under SARDP- NE , under EPC Mode in the state of Assam Pkg-IV Structures & Toll Plaza is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹279.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of Balance Work of the 4-Laning of the Section from Jorhat to Jhanj"?
- Construction of Balance Work of the 4-Laning of the Section from Jorhat to Jhanji of NH-37 Old from Km 453.000 to Km 490.800, under SARDP- NE , under EPC Mode in the state of Assam Pkg-IV Structures & Toll Plaza is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹279 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹279 Cr has not been significantly revised. Expenditure: ₹399 Cr (142.8% of cost). Data as of 2026-06.
- QWhich ministry is responsible for this project?
- Construction of Balance Work of the 4-Laning of the Section is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618444. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Balance Work of the 4-Laning of the Section is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.