Construction of Balance Work of 4-Laning of the Section from Jhanji to Demow of NH-37 Old from Km 501.800 to Km 514.800 13.000 Km, under SARDP- NE under EPC Mode in the state of Assam Pkg-II Road Works
Original Cost
₹509 Cr
Baseline estimate
Revised Cost
₹543 Cr
Latest approved cost
Expenditure
₹114 Cr
Spent to date
Utilization
21.0%
Of revised budget
Cost Status
+6.7%
+₹34 Cr increase
Remaining
₹429 Cr
Budget left
Budget Utilization
21.0%Spent
₹114 Cr
Remaining
₹429 Cr
Total
₹543 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹509 Cr
Revised Cost
₹543 Cr
Increase
+₹34 Cr
Escalation
+6.7%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
22/01/2026
Revised Completion
31/10/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹34 Cr (6.7%) from the original estimate of ₹509 Cr.
Expenditure stands at ₹114 Cr, which is 21.0% of the revised project cost.
Remaining budget: ₹429 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of Balance Work of 4-Laning of the Section from Jhanji to Demow of NH-37 Old from Km 501.800 to Km 514.800 13.000 Km, under SARDP- NE under EPC Mode in the state of Assam Pkg-II Road Works is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹509.00 Cr, later revised to ₹542.87 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of Balance Work of 4-Laning of the Section from Jhanji to Demow of "?
- Construction of Balance Work of 4-Laning of the Section from Jhanji to Demow of NH-37 Old from Km 501.800 to Km 514.800 13.000 Km, under SARDP- NE under EPC Mode in the state of Assam Pkg-II Road Works is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹509 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹509 Cr and has been revised to ₹543 Cr — a cost overrun of +6.7%. Expenditure to date: ₹114 Cr (21.0% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of Balance Work of 4-Laning of the Section from is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619013. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Balance Work of 4-Laning of the Section from is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.