Roads & HighwaysIPM · Central Project +6.7% overrun#619013

Construction of Balance Work of 4-Laning of the Section from Jhanji to Demow of NH-37 Old from Km 501.800 to Km 514.800 13.000 Km, under SARDP- NE under EPC Mode in the state of Assam Pkg-II Road Works

Ministry of Road Transport & HighwaysAssam
Revised Cost: ₹543 CrUtilization: 21.0%Overrun: +₹34 Cr

Original Cost

₹509 Cr

Baseline estimate

+7% overrun

Revised Cost

₹543 Cr

Latest approved cost

Expenditure

₹114 Cr

Spent to date

Utilization

21.0%

Of revised budget

Escalated

Cost Status

+6.7%

+₹34 Cr increase

Remaining

₹429 Cr

Budget left

Budget Utilization

21.0%
0%25%50%75%100%

Spent

₹114 Cr

Remaining

₹429 Cr

Total

₹543 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹509 Cr

Revised Cost

₹543 Cr

Increase

+₹34 Cr

Escalation

+6.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

22/01/2026

Revised Completion

31/10/2026

Completed

Project Details

Project Code619013
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAssam
Data Month2026-08

Financial Summary

Original Cost₹509 Cr
Revised Cost₹543 Cr
Expenditure₹114 Cr
Original End Date22/01/2026
Revised Date31/10/2026

Project Intelligence

Cost has increased by ₹34 Cr (6.7%) from the original estimate of ₹509 Cr.

Expenditure stands at ₹114 Cr, which is 21.0% of the revised project cost.

Remaining budget: ₹429 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of Balance Work of 4-Laning of the Section from Jhanji to Demow of NH-37 Old from Km 501.800 to Km 514.800 13.000 Km, under SARDP- NE under EPC Mode in the state of Assam Pkg-II Road Works is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹509.00 Cr, later revised to ₹542.87 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of Balance Work of 4-Laning of the Section from Jhanji to Demow of "?
Construction of Balance Work of 4-Laning of the Section from Jhanji to Demow of NH-37 Old from Km 501.800 to Km 514.800 13.000 Km, under SARDP- NE under EPC Mode in the state of Assam Pkg-II Road Works is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹509 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹509 Cr and has been revised to ₹543 Cr — a cost overrun of +6.7%. Expenditure to date: ₹114 Cr (21.0% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of Balance Work of 4-Laning of the Section from is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619013. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Balance Work of 4-Laning of the Section from is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.