Construction of Balance Work of 4-Laning of NH-37 Section between End of Moran Bypass to Bogibeel junction near Lapetketa Km. 561.700-Km. 580.875 under SARDP-NE, Phase 'A' in the State of Assam on EPC mode Pkg-I Road works & Toll Plaza
Original Cost
₹274 Cr
Baseline estimate
Revised Cost
₹274 Cr
Latest approved cost
Expenditure
₹117 Cr
Spent to date
Utilization
42.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹157 Cr
Budget left
Budget Utilization
42.6%Spent
₹117 Cr
Remaining
₹157 Cr
Total
₹274 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
14/03/2025
Revised Completion
11/08/2025
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹274 Cr — no cost escalation recorded.
Expenditure stands at ₹117 Cr, which is 42.6% of the revised project cost.
Remaining budget: ₹157 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of Balance Work of 4-Laning of NH-37 Section between End of Moran Bypass to Bogibeel junction near Lapetketa Km. 561.700-Km. 580.875 under SARDP-NE, Phase 'A' in the State of Assam on EPC mode Pkg-I Road works & Toll Plaza is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹274.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of Balance Work of 4-Laning of NH-37 Section between End of Moran B"?
- Construction of Balance Work of 4-Laning of NH-37 Section between End of Moran Bypass to Bogibeel junction near Lapetketa Km. 561.700-Km. 580.875 under SARDP-NE, Phase 'A' in the State of Assam on EPC mode Pkg-I Road works & Toll Plaza is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹274 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹274 Cr has not been significantly revised. Expenditure: ₹117 Cr (42.6% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of Balance Work of 4-Laning of NH-37 Section be is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618437. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Balance Work of 4-Laning of NH-37 Section be is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.