Original Cost
₹274 Cr
Baseline estimate
Revised Cost
₹274 Cr
Latest approved cost
Expenditure
₹93 Cr
Spent to date
Utilization
34.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹181 Cr
Budget left
Spent
₹93 Cr
Remaining
₹181 Cr
Total
₹274 Cr
Project Approved
Construction / Implementation
Original End Date
14/03/2025
Revised Completion
11/08/2025
Completed
Project is within original budget of ₹274 Cr — no cost escalation recorded.
Expenditure stands at ₹93 Cr, which is 34.1% of the revised project cost.
Remaining budget: ₹181 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.