Construction of Balance work for 2-lane with hard shoulder of Peren- Dimapur section on NH-129A from Design Km 126.775 to Km 146.208 Length 19.433 Km in the state of Nagaland on EPC mode under NHO-TSP Package-II
Original Cost
₹259 Cr
Baseline estimate
Revised Cost
₹259 Cr
Latest approved cost
Expenditure
₹136 Cr
Spent to date
Utilization
52.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹123 Cr
Budget left
Budget Utilization
52.5%Spent
₹136 Cr
Remaining
₹123 Cr
Total
₹259 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
09/09/2025
Revised Completion
09/09/2025
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹259 Cr — no cost escalation recorded.
Expenditure stands at ₹136 Cr, which is 52.5% of the revised project cost.
Remaining budget: ₹123 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of Balance work for 2-lane with hard shoulder of Peren- Dimapur section on NH-129A from Design Km 126.775 to Km 146.208 Length 19.433 Km in the state of Nagaland on EPC mode under NHO-TSP Package-II is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹259.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of Balance work for 2-lane with hard shoulder of Peren- Dimapur sec"?
- Construction of Balance work for 2-lane with hard shoulder of Peren- Dimapur section on NH-129A from Design Km 126.775 to Km 146.208 Length 19.433 Km in the state of Nagaland on EPC mode under NHO-TSP Package-II is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Nagaland. Original cost: ₹259 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹259 Cr has not been significantly revised. Expenditure: ₹136 Cr (52.5% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of Balance work for 2-lane with hard shoulder o is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618414. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Balance work for 2-lane with hard shoulder o is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.