Roads & HighwaysIPM · Central Project#618430

Construction of alternative highway to Gangtok in Sikkim via Bagrakot -Chuikhim-Nimbong -Kafer-Bakhim-Algarah-Rhenock in the State of West Bengal and from Rhenok-Rorathang-Pakyong along with spur from Aritar-Rolep-Menla in the State of Sikkim from Km 0.00 to Km 13.00 of Bagrakot -Kafer section of NH 717A on EPC Mode under Phase-A of SARDP-NE in the State of West Bengal PKG- IVA

Ministry of Road Transport & HighwaysWest Bengal
Revised Cost: ₹403 CrUtilization: 65.0%

Original Cost

₹403 Cr

Baseline estimate

On budget

Revised Cost

₹403 Cr

Latest approved cost

Expenditure

₹262 Cr

Spent to date

Utilization

65.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹141 Cr

Budget left

Budget Utilization

65.0%
0%25%50%75%100%

Spent

₹262 Cr

Remaining

₹141 Cr

Total

₹403 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

03/04/2022

Revised Completion

30/08/2026

Completed

Project Details

Project Code618430
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateWest Bengal
Data Month2026-08

Financial Summary

Original Cost₹403 Cr
Revised Cost₹403 Cr
Expenditure₹262 Cr
Original End Date03/04/2022
Revised Date30/08/2026

Project Intelligence

Project is within original budget of ₹403 Cr — no cost escalation recorded.

Expenditure stands at ₹262 Cr, which is 65.0% of the revised project cost.

Remaining budget: ₹141 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of alternative highway to Gangtok in Sikkim via Bagrakot -Chuikhim-Nimbong -Kafer-Bakhim-Algarah-Rhenock in the State of West Bengal and from Rhenok-Rorathang-Pakyong along with spur from Aritar-Rolep-Menla in the State of Sikkim from Km 0.00 to Km 13.00 of Bagrakot -Kafer section of NH 717A on EPC Mode under Phase-A of SARDP-NE in the State of West Bengal PKG- IVA is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹403.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of alternative highway to Gangtok in Sikkim via Bagrakot -Chuikhim-"?
Construction of alternative highway to Gangtok in Sikkim via Bagrakot -Chuikhim-Nimbong -Kafer-Bakhim-Algarah-Rhenock in the State of West Bengal and from Rhenok-Rorathang-Pakyong along with spur from Aritar-Rolep-Menla in the State of Sikkim from Km 0.00 to Km 13.00 of Bagrakot -Kafer section of NH 717A on EPC Mode under Phase-A of SARDP-NE in the State of West Bengal PKG- IVA is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: West Bengal. Original cost: ₹403 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹403 Cr has not been significantly revised. Expenditure: ₹262 Cr (65.0% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of alternative highway to Gangtok in Sikkim via is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618430. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of alternative highway to Gangtok in Sikkim via is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.