Original Cost
₹1535 Cr
Baseline estimate
Revised Cost
₹1473 Cr
Latest approved cost
Expenditure
₹313 Cr
Spent to date
Utilization
21.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1160 Cr
Budget left
Spent
₹313 Cr
Remaining
₹1160 Cr
Total
₹1473 Cr
Project Approved
Construction / Implementation
Original End Date
31/12/2027
Revised Completion
31/12/2027
Completed
Project is within original budget of ₹1535 Cr — no cost escalation recorded.
Expenditure stands at ₹313 Cr, which is 21.3% of the revised project cost.
Remaining budget: ₹1160 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.