Original Cost
₹1081 Cr
Baseline estimate
Revised Cost
₹1116 Cr
Latest approved cost
Expenditure
₹411 Cr
Spent to date
Utilization
36.8%
Of revised budget
Cost Status
+3.3%
+₹35 Cr increase
Remaining
₹705 Cr
Budget left
Spent
₹411 Cr
Remaining
₹705 Cr
Total
₹1116 Cr
Original Cost
₹1081 Cr
Revised Cost
₹1116 Cr
Increase
+₹35 Cr
Escalation
+3.3%
Project Approved
Construction / Implementation
Original End Date
29/03/2024
Revised Completion
31/12/2025
Completed
Cost has increased by ₹35 Cr (3.3%) from the original estimate of ₹1081 Cr.
Expenditure stands at ₹411 Cr, which is 36.8% of the revised project cost.
Remaining budget: ₹705 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.