Original Cost
₹1122 Cr
Baseline estimate
Revised Cost
₹1870 Cr
Latest approved cost
Expenditure
₹52 Cr
Spent to date
Utilization
2.8%
Of revised budget
Cost Status
+66.6%
+₹748 Cr increase
Remaining
₹1817 Cr
Budget left
Spent
₹52 Cr
Remaining
₹1817 Cr
Total
₹1870 Cr
Original Cost
₹1122 Cr
Revised Cost
₹1870 Cr
Increase
+₹748 Cr
Escalation
+66.6%
Project Approved
Construction / Implementation
Original End Date
23/06/2028
Revised Completion
23/06/2028
Completed
Cost has increased by ₹748 Cr (66.6%) from the original estimate of ₹1122 Cr.
Expenditure stands at ₹52 Cr, which is 2.8% of the revised project cost.
Remaining budget: ₹1817 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.