Roads & HighwaysIPM · Central Project#618320

Construction of 4-Laning of N. Kawnpui N. Mualvum Mualkhang via Khamrang Village section Package-7 of NH-6 from Existing Chainage km 127200 to km 142000 Design Chainage km 111850 to km 123400 on Silchar - Vairengte - Sairang road in the State of Mizoram on EPC mode

Ministry of Road Transport & HighwaysMizoram
Revised Cost: ₹866 CrUtilization: 22.9%

Original Cost

₹866 Cr

Baseline estimate

On budget

Revised Cost

₹866 Cr

Latest approved cost

Expenditure

₹198 Cr

Spent to date

Utilization

22.9%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹668 Cr

Budget left

Budget Utilization

22.9%
0%25%50%75%100%

Spent

₹198 Cr

Remaining

₹668 Cr

Total

₹866 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

28/10/2028

Revised Completion

Completed

Project Details

Project Code618320
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMizoram
Data Month2026-08

Financial Summary

Original Cost₹866 Cr
Revised Cost₹866 Cr
Expenditure₹198 Cr
Original End Date28/10/2028
Revised DateN/A

Project Intelligence

Project is within original budget of ₹866 Cr — no cost escalation recorded.

Expenditure stands at ₹198 Cr, which is 22.9% of the revised project cost.

Remaining budget: ₹668 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of 4-Laning of N. Kawnpui N. Mualvum Mualkhang via Khamrang Village section Package-7 of NH-6 from Existing Chainage km 127200 to km 142000 Design Chainage km 111850 to km 123400 on Silchar - Vairengte - Sairang road in the State of Mizoram on EPC mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹866.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of 4-Laning of N. Kawnpui N. Mualvum Mualkhang via Khamrang Village"?
Construction of 4-Laning of N. Kawnpui N. Mualvum Mualkhang via Khamrang Village section Package-7 of NH-6 from Existing Chainage km 127200 to km 142000 Design Chainage km 111850 to km 123400 on Silchar - Vairengte - Sairang road in the State of Mizoram on EPC mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Mizoram. Original cost: ₹866 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹866 Cr has not been significantly revised. Expenditure: ₹198 Cr (22.9% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of 4-Laning of N. Kawnpui N. Mualvum Mualkhang is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618320. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 4-Laning of N. Kawnpui N. Mualvum Mualkhang is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.