Construction of 4 lane Gauripur Bypass Starting bfrom Km 852.56 of NH-31Dumardoha Pt-II and Terminating at Km 862.17 Baladmara via. Khudimari Pt.- II, Fulkumari, Charaldanga, Sajuakuti,Geramari Pt.-III and finally meeting at km 862.17 of NH-17New/ NH-31Old in the State of Assam under EPC Mode Job no. 31/AS/ 2023-24/265
Original Cost
₹421 Cr
Baseline estimate
Revised Cost
₹421 Cr
Latest approved cost
Expenditure
₹55 Cr
Spent to date
Utilization
13.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹366 Cr
Budget left
Budget Utilization
13.1%Spent
₹55 Cr
Remaining
₹366 Cr
Total
₹421 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
24/10/2026
Revised Completion
31/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹421 Cr — no cost escalation recorded.
Expenditure stands at ₹55 Cr, which is 13.1% of the revised project cost.
Remaining budget: ₹366 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of 4 lane Gauripur Bypass Starting bfrom Km 852.56 of NH-31Dumardoha Pt-II and Terminating at Km 862.17 Baladmara via. Khudimari Pt.- II, Fulkumari, Charaldanga, Sajuakuti,Geramari Pt.-III and finally meeting at km 862.17 of NH-17New/ NH-31Old in the State of Assam under EPC Mode Job no. 31/AS/ 2023-24/265 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹421.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of 4 lane Gauripur Bypass Starting bfrom Km 852.56 of NH-31Dumardoh"?
- Construction of 4 lane Gauripur Bypass Starting bfrom Km 852.56 of NH-31Dumardoha Pt-II and Terminating at Km 862.17 Baladmara via. Khudimari Pt.- II, Fulkumari, Charaldanga, Sajuakuti,Geramari Pt.-III and finally meeting at km 862.17 of NH-17New/ NH-31Old in the State of Assam under EPC Mode Job no. 31/AS/ 2023-24/265 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹421 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹421 Cr has not been significantly revised. Expenditure: ₹55 Cr (13.1% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of 4 lane Gauripur Bypass Starting bfrom Km 852 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617896. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 4 lane Gauripur Bypass Starting bfrom Km 852 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.