Construction of 4 lane Bypass to Nalgonda Town lrorn Km 000 Existing Ch. 181590 to Km 14.00 Existing Ch. 28/685 ol Nakrekal to Nagarjunsagar Section of NH -565 in the State of Telangara on EPC under Annual Plan 2024 -25
Original Cost
₹516 Cr
Baseline estimate
Revised Cost
₹516 Cr
Latest approved cost
Expenditure
₹262 Cr
Spent to date
Utilization
50.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹254 Cr
Budget left
Budget Utilization
50.8%Spent
₹262 Cr
Remaining
₹254 Cr
Total
₹516 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
06/10/2027
Revised Completion
06/10/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹516 Cr — no cost escalation recorded.
Expenditure stands at ₹262 Cr, which is 50.8% of the revised project cost.
Remaining budget: ₹254 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of 4 lane Bypass to Nalgonda Town lrorn Km 000 Existing Ch. 181590 to Km 14.00 Existing Ch. 28/685 ol Nakrekal to Nagarjunsagar Section of NH -565 in the State of Telangara on EPC under Annual Plan 2024 -25 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹516.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of 4 lane Bypass to Nalgonda Town lrorn Km 000 Existing Ch. 181590 "?
- Construction of 4 lane Bypass to Nalgonda Town lrorn Km 000 Existing Ch. 181590 to Km 14.00 Existing Ch. 28/685 ol Nakrekal to Nagarjunsagar Section of NH -565 in the State of Telangara on EPC under Annual Plan 2024 -25 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Telangana. Original cost: ₹516 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹516 Cr has not been significantly revised. Expenditure: ₹262 Cr (50.8% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of 4 lane Bypass to Nalgonda Town lrorn Km 000 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619253. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 4 lane Bypass to Nalgonda Town lrorn Km 000 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.