Original Cost
₹316 Cr
Baseline estimate
Revised Cost
₹316 Cr
Latest approved cost
Expenditure
₹228 Cr
Spent to date
Utilization
72.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹88 Cr
Budget left
Spent
₹228 Cr
Remaining
₹88 Cr
Total
₹316 Cr
Project Approved
Construction / Implementation
Original End Date
20/01/2025
Revised Completion
31/07/2026
Completed
Project is within original budget of ₹316 Cr — no cost escalation recorded.
Expenditure stands at ₹228 Cr, which is 72.2% of the revised project cost.
Remaining budget: ₹88 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.