Roads & HighwaysIPM · Central Project#618388

Construction of 2-laning with Hard shoulder road of Ukhrul - Tolloi - Tadubi section of NH-102A from Design Chainage 50.850 km to 81.870 km in the State of Manipur on EPC mode under NHO-TSP Package -3

Ministry of Road Transport & HighwaysManipur
Revised Cost: ₹316 CrUtilization: 81.5%

Original Cost

₹316 Cr

Baseline estimate

On budget

Revised Cost

₹316 Cr

Latest approved cost

Expenditure

₹257 Cr

Spent to date

Utilization

81.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹59 Cr

Budget left

Budget Utilization

81.5%
0%25%50%75%100%

Spent

₹257 Cr

Remaining

₹59 Cr

Total

₹316 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

20/01/2025

Revised Completion

31/12/2026

Completed

Project Details

Project Code618388
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateManipur
Data Month2026-08

Financial Summary

Original Cost₹316 Cr
Revised Cost₹316 Cr
Expenditure₹257 Cr
Original End Date20/01/2025
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹316 Cr — no cost escalation recorded.

Expenditure stands at ₹257 Cr, which is 81.5% of the revised project cost.

Remaining budget: ₹59 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of 2-laning with Hard shoulder road of Ukhrul - Tolloi - Tadubi section of NH-102A from Design Chainage 50.850 km to 81.870 km in the State of Manipur on EPC mode under NHO-TSP Package -3 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹316.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of 2-laning with Hard shoulder road of Ukhrul - Tolloi - Tadubi sec"?
Construction of 2-laning with Hard shoulder road of Ukhrul - Tolloi - Tadubi section of NH-102A from Design Chainage 50.850 km to 81.870 km in the State of Manipur on EPC mode under NHO-TSP Package -3 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Manipur. Original cost: ₹316 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹316 Cr has not been significantly revised. Expenditure: ₹257 Cr (81.5% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of 2-laning with Hard shoulder road of Ukhrul - is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618388. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 2-laning with Hard shoulder road of Ukhrul - is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.