Construction of 2 laning with Hard shoulder of Peren-Dimapur section on NH 129A from Design Km 146.208 to Km 163.592 Length- 17.384 km in the state of Nagaland on EPC mode under NHO-TSP Package-III
Original Cost
₹178 Cr
Baseline estimate
Revised Cost
₹199 Cr
Latest approved cost
Expenditure
₹112 Cr
Spent to date
Utilization
56.2%
Of revised budget
Cost Status
+11.8%
+₹21 Cr increase
Remaining
₹87 Cr
Budget left
Budget Utilization
56.2%Spent
₹112 Cr
Remaining
₹87 Cr
Total
₹199 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹178 Cr
Revised Cost
₹199 Cr
Increase
+₹21 Cr
Escalation
+11.8%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
06/06/2025
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹21 Cr (11.8%) from the original estimate of ₹178 Cr.
Expenditure stands at ₹112 Cr, which is 56.2% of the revised project cost.
Remaining budget: ₹87 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of 2 laning with Hard shoulder of Peren-Dimapur section on NH 129A from Design Km 146.208 to Km 163.592 Length- 17.384 km in the state of Nagaland on EPC mode under NHO-TSP Package-III is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹178.00 Cr, later revised to ₹199.02 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of 2 laning with Hard shoulder of Peren-Dimapur section on NH 129A "?
- Construction of 2 laning with Hard shoulder of Peren-Dimapur section on NH 129A from Design Km 146.208 to Km 163.592 Length- 17.384 km in the state of Nagaland on EPC mode under NHO-TSP Package-III is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Nagaland. Original cost: ₹178 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹178 Cr and has been revised to ₹199 Cr — a cost overrun of +11.8%. Expenditure to date: ₹112 Cr (56.2% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of 2 laning with Hard shoulder of Peren-Dimapur is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618413. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 2 laning with Hard shoulder of Peren-Dimapur is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.