Original Cost
₹178 Cr
Baseline estimate
Revised Cost
₹199 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
+11.8%
+₹21 Cr increase
Remaining
₹199 Cr
Budget left
Spent
₹0 Cr
Remaining
₹199 Cr
Total
₹199 Cr
Original Cost
₹178 Cr
Revised Cost
₹199 Cr
Increase
+₹21 Cr
Escalation
+11.8%
Project Approved
Construction / Implementation
Original End Date
06/06/2025
Revised Completion
06/06/2026
Completed
Cost has increased by ₹21 Cr (11.8%) from the original estimate of ₹178 Cr.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹199 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.