Roads & HighwaysIPM · Central Project +11.8% overrun#618413

Construction of 2 laning with Hard shoulder of Peren-Dimapur section on NH 129A from Design Km 146.208 to Km 163.592 Length- 17.384 km in the state of Nagaland on EPC mode under NHO-TSP Package-III

Ministry of Road Transport & HighwaysNagaland
Revised Cost: ₹199 CrUtilization: 56.2%Overrun: +₹21 Cr

Original Cost

₹178 Cr

Baseline estimate

+12% overrun

Revised Cost

₹199 Cr

Latest approved cost

Expenditure

₹112 Cr

Spent to date

Utilization

56.2%

Of revised budget

Escalated

Cost Status

+11.8%

+₹21 Cr increase

Remaining

₹87 Cr

Budget left

Budget Utilization

56.2%
0%25%50%75%100%

Spent

₹112 Cr

Remaining

₹87 Cr

Total

₹199 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹178 Cr

Revised Cost

₹199 Cr

Increase

+₹21 Cr

Escalation

+11.8%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

06/06/2025

Revised Completion

30/09/2026

Completed

Project Details

Project Code618413
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateNagaland
Data Month2026-08

Financial Summary

Original Cost₹178 Cr
Revised Cost₹199 Cr
Expenditure₹112 Cr
Original End Date06/06/2025
Revised Date30/09/2026

Project Intelligence

Cost has increased by ₹21 Cr (11.8%) from the original estimate of ₹178 Cr.

Expenditure stands at ₹112 Cr, which is 56.2% of the revised project cost.

Remaining budget: ₹87 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of 2 laning with Hard shoulder of Peren-Dimapur section on NH 129A from Design Km 146.208 to Km 163.592 Length- 17.384 km in the state of Nagaland on EPC mode under NHO-TSP Package-III is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹178.00 Cr, later revised to ₹199.02 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of 2 laning with Hard shoulder of Peren-Dimapur section on NH 129A "?
Construction of 2 laning with Hard shoulder of Peren-Dimapur section on NH 129A from Design Km 146.208 to Km 163.592 Length- 17.384 km in the state of Nagaland on EPC mode under NHO-TSP Package-III is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Nagaland. Original cost: ₹178 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹178 Cr and has been revised to ₹199 Cr — a cost overrun of +11.8%. Expenditure to date: ₹112 Cr (56.2% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of 2 laning with Hard shoulder of Peren-Dimapur is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618413. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 2 laning with Hard shoulder of Peren-Dimapur is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.