Original Cost
₹741 Cr
Baseline estimate
Revised Cost
₹741 Cr
Latest approved cost
Expenditure
₹432 Cr
Spent to date
Utilization
58.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹309 Cr
Budget left
Spent
₹432 Cr
Remaining
₹309 Cr
Total
₹741 Cr
Project Approved
Construction / Implementation
Original End Date
09/01/2023
Revised Completion
31/12/2026
Completed
Project is within original budget of ₹741 Cr — no cost escalation recorded.
Expenditure stands at ₹432 Cr, which is 58.3% of the revised project cost.
Remaining budget: ₹309 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.