Roads & HighwaysIPM · Central Project#618363

Construction of 2-laning with hard shoulder configuration of Chhumkhum to Tlabung from Design Chainage Km 37.420 to Km 74.950 of NH-302 in Mizoram under Bharatmala Pariyojana on EPC mode [Pkg-B]

Ministry of Road Transport & HighwaysMizoram
Revised Cost: ₹741 CrUtilization: 66.7%

Original Cost

₹741 Cr

Baseline estimate

On budget

Revised Cost

₹741 Cr

Latest approved cost

Expenditure

₹494 Cr

Spent to date

Utilization

66.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹247 Cr

Budget left

Budget Utilization

66.7%
0%25%50%75%100%

Spent

₹494 Cr

Remaining

₹247 Cr

Total

₹741 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

09/01/2023

Revised Completion

31/12/2026

Completed

Project Details

Project Code618363
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMizoram
Data Month2026-08

Financial Summary

Original Cost₹741 Cr
Revised Cost₹741 Cr
Expenditure₹494 Cr
Original End Date09/01/2023
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹741 Cr — no cost escalation recorded.

Expenditure stands at ₹494 Cr, which is 66.7% of the revised project cost.

Remaining budget: ₹247 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of 2-laning with hard shoulder configuration of Chhumkhum to Tlabung from Design Chainage Km 37.420 to Km 74.950 of NH-302 in Mizoram under Bharatmala Pariyojana on EPC mode [Pkg-B] is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹741.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of 2-laning with hard shoulder configuration of Chhumkhum to Tlabun"?
Construction of 2-laning with hard shoulder configuration of Chhumkhum to Tlabung from Design Chainage Km 37.420 to Km 74.950 of NH-302 in Mizoram under Bharatmala Pariyojana on EPC mode [Pkg-B] is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Mizoram. Original cost: ₹741 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹741 Cr has not been significantly revised. Expenditure: ₹494 Cr (66.7% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of 2-laning with hard shoulder configuration of is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618363. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 2-laning with hard shoulder configuration of is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.