Original Cost
₹247 Cr
Baseline estimate
Revised Cost
₹247 Cr
Latest approved cost
Expenditure
₹111 Cr
Spent to date
Utilization
44.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹136 Cr
Budget left
Spent
₹111 Cr
Remaining
₹136 Cr
Total
₹247 Cr
Project Approved
Construction / Implementation
Original End Date
06/05/2020
Revised Completion
31/12/2026
Completed
Project is within original budget of ₹247 Cr — no cost escalation recorded.
Expenditure stands at ₹111 Cr, which is 44.9% of the revised project cost.
Remaining budget: ₹136 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.