Original Cost
₹232 Cr
Baseline estimate
Revised Cost
₹351 Cr
Latest approved cost
Expenditure
₹16 Cr
Spent to date
Utilization
4.6%
Of revised budget
Cost Status
+51.2%
+₹119 Cr increase
Remaining
₹335 Cr
Budget left
Spent
₹16 Cr
Remaining
₹335 Cr
Total
₹351 Cr
Original Cost
₹232 Cr
Revised Cost
₹351 Cr
Increase
+₹119 Cr
Escalation
+51.2%
Project Approved
Construction / Implementation
Original End Date
08/11/2026
Revised Completion
08/11/2026
Completed
Cost has increased by ₹119 Cr (51.2%) from the original estimate of ₹232 Cr.
Expenditure stands at ₹16 Cr, which is 4.6% of the revised project cost.
Remaining budget: ₹335 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.