Roads & HighwaysIPM · Central Project +51.2% overrun#618293

Construction of 2-Lane with paved shoulder of Kohima-Bypass Road connecting NH-39New NH-02, NH-150New NH-02, NH-61New NH-29 and NH-39New NH-02 from design Km 0.00 to Km 10.500 in the State of Nagaland under SARDP-NE on EPC Mode Package-1 -Balance work

Ministry of Road Transport & HighwaysNagaland
Revised Cost: ₹351 CrUtilization: 34.5%Overrun: +₹119 Cr

Original Cost

₹232 Cr

Baseline estimate

+51% overrun

Revised Cost

₹351 Cr

Latest approved cost

Expenditure

₹121 Cr

Spent to date

Utilization

34.5%

Of revised budget

Escalated

Cost Status

+51.2%

+₹119 Cr increase

Remaining

₹230 Cr

Budget left

Budget Utilization

34.5%
0%25%50%75%100%

Spent

₹121 Cr

Remaining

₹230 Cr

Total

₹351 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹232 Cr

Revised Cost

₹351 Cr

Increase

+₹119 Cr

Escalation

+51.2%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

08/11/2026

Revised Completion

08/11/2026

Completed

Project Details

Project Code618293
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateNagaland
Data Month2026-08

Financial Summary

Original Cost₹232 Cr
Revised Cost₹351 Cr
Expenditure₹121 Cr
Original End Date08/11/2026
Revised Date08/11/2026

Project Intelligence

Cost has increased by ₹119 Cr (51.2%) from the original estimate of ₹232 Cr.

Expenditure stands at ₹121 Cr, which is 34.5% of the revised project cost.

Remaining budget: ₹230 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of 2-Lane with paved shoulder of Kohima-Bypass Road connecting NH-39New NH-02, NH-150New NH-02, NH-61New NH-29 and NH-39New NH-02 from design Km 0.00 to Km 10.500 in the State of Nagaland under SARDP-NE on EPC Mode Package-1 -Balance work is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹232.00 Cr, later revised to ₹350.88 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of 2-Lane with paved shoulder of Kohima-Bypass Road connecting NH-3"?
Construction of 2-Lane with paved shoulder of Kohima-Bypass Road connecting NH-39New NH-02, NH-150New NH-02, NH-61New NH-29 and NH-39New NH-02 from design Km 0.00 to Km 10.500 in the State of Nagaland under SARDP-NE on EPC Mode Package-1 -Balance work is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Nagaland. Original cost: ₹232 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹232 Cr and has been revised to ₹351 Cr — a cost overrun of +51.2%. Expenditure to date: ₹121 Cr (34.5% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of 2-Lane with paved shoulder of Kohima-Bypass is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618293. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 2-Lane with paved shoulder of Kohima-Bypass is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.