Construction of 2-lane with Paved shoulder of Kohima- Bypass Road Connecting NH-39New NH-02, NH-150New NH-02, NH-61New NH-29, NH-39New NH-02 from Design Km 32.00 to Design Km 43.454Design Length-11.454 Km in the State of Nagaland under SARDP-NE on EPC Mode Package-IV
Original Cost
₹202 Cr
Baseline estimate
Revised Cost
₹202 Cr
Latest approved cost
Expenditure
₹102 Cr
Spent to date
Utilization
50.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹100 Cr
Budget left
Budget Utilization
50.7%Spent
₹102 Cr
Remaining
₹100 Cr
Total
₹202 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
17/04/2022
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹202 Cr — no cost escalation recorded.
Expenditure stands at ₹102 Cr, which is 50.7% of the revised project cost.
Remaining budget: ₹100 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of 2-lane with Paved shoulder of Kohima- Bypass Road Connecting NH-39New NH-02, NH-150New NH-02, NH-61New NH-29, NH-39New NH-02 from Design Km 32.00 to Design Km 43.454Design Length-11.454 Km in the State of Nagaland under SARDP-NE on EPC Mode Package-IV is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹202.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of 2-lane with Paved shoulder of Kohima- Bypass Road Connecting NH-"?
- Construction of 2-lane with Paved shoulder of Kohima- Bypass Road Connecting NH-39New NH-02, NH-150New NH-02, NH-61New NH-29, NH-39New NH-02 from Design Km 32.00 to Design Km 43.454Design Length-11.454 Km in the State of Nagaland under SARDP-NE on EPC Mode Package-IV is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Nagaland. Original cost: ₹202 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹202 Cr has not been significantly revised. Expenditure: ₹102 Cr (50.7% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of 2-lane with Paved shoulder of Kohima- Bypass is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618290. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of 2-lane with Paved shoulder of Kohima- Bypass is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.