Original Cost
₹411 Cr
Baseline estimate
Revised Cost
₹411 Cr
Latest approved cost
Expenditure
₹67 Cr
Spent to date
Utilization
16.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹344 Cr
Budget left
Spent
₹67 Cr
Remaining
₹344 Cr
Total
₹411 Cr
Project Approved
Construction / Implementation
Original End Date
11/05/2024
Revised Completion
31/07/2026
Completed
Project is within original budget of ₹411 Cr — no cost escalation recorded.
Expenditure stands at ₹67 Cr, which is 16.2% of the revised project cost.
Remaining budget: ₹344 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.