Original Cost
₹318 Cr
Baseline estimate
Revised Cost
₹318 Cr
Latest approved cost
Expenditure
₹6 Cr
Spent to date
Utilization
1.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹312 Cr
Budget left
Spent
₹6 Cr
Remaining
₹312 Cr
Total
₹318 Cr
Project Approved
Construction / Implementation
Original End Date
14/04/2025
Revised Completion
06/02/2027
Completed
Project is within original budget of ₹318 Cr — no cost escalation recorded.
Expenditure stands at ₹6 Cr, which is 1.9% of the revised project cost.
Remaining budget: ₹312 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.