Original Cost
₹3207 Cr
Baseline estimate
Revised Cost
₹3207 Cr
Latest approved cost
Expenditure
₹418 Cr
Spent to date
Utilization
13.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹2789 Cr
Budget left
Spent
₹418 Cr
Remaining
₹2789 Cr
Total
₹3207 Cr
Project Approved
Construction / Implementation
Original End Date
30/06/2030
Revised Completion
30/06/2030
Completed
Project is within original budget of ₹3207 Cr — no cost escalation recorded.
Expenditure stands at ₹418 Cr, which is 13.0% of the revised project cost.
Remaining budget: ₹2789 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.