Original Cost
₹1424 Cr
Baseline estimate
Revised Cost
₹1424 Cr
Latest approved cost
Expenditure
₹102 Cr
Spent to date
Utilization
7.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1322 Cr
Budget left
Spent
₹102 Cr
Remaining
₹1322 Cr
Total
₹1424 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2028
Revised Completion
Completed
Project is within original budget of ₹1424 Cr — no cost escalation recorded.
Expenditure stands at ₹102 Cr, which is 7.2% of the revised project cost.
Remaining budget: ₹1322 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.