RailwaysIPM · Central Project#611969

Choranda Motikoral 18 Kms

Ministry of RailwaysGujarat
Revised Cost: ₹246 CrUtilization: 0.0%

Original Cost

₹246 Cr

Baseline estimate

On budget

Revised Cost

₹246 Cr

Latest approved cost

Expenditure

₹0 Cr

Spent to date

Utilization

0.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹246 Cr

Budget left

Budget Utilization

0.0%
0%25%50%75%100%

Spent

₹0 Cr

Remaining

₹246 Cr

Total

₹246 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/10/2026

Revised Completion

Completed

Project Details

Project Code611969
SectorRailways
MinistryMinistry of Railways
StateGujarat
Data Month2025-08

Financial Summary

Original Cost₹246 Cr
Revised Cost₹246 Cr
Expenditure₹0 Cr
Original End Date30/10/2026
Revised DateN/A

Project Intelligence

Project is within original budget of ₹246 Cr — no cost escalation recorded.

Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.

Remaining budget: ₹246 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Choranda Motikoral 18 Kms is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹246.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Choranda Motikoral 18 Kms"?
Choranda Motikoral 18 Kms is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Gujarat. Original cost: ₹246 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹246 Cr has not been significantly revised. Expenditure: ₹0 Cr (N/A% of cost). Data as of 2025-08.
QWhich ministry is responsible for this project?
Choranda Motikoral 18 Kms is under the Ministry of Railways in the Railways sector. Project code: 611969. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Choranda Motikoral 18 Kms is one of several Bihar projects tracked under the Railways sector on the IPM system.