RailwaysIPM · Central Project +11.1% overrun#705454

Chhota Udepur-Dhar 157 km

Ministry of RailwaysMadhya Pradesh
Revised Cost: ₹1994 CrUtilization: 93.4%Overrun: +₹200 Cr

Original Cost

₹1794 Cr

Baseline estimate

+11% overrun

Revised Cost

₹1994 Cr

Latest approved cost

Expenditure

₹1862 Cr

Spent to date

Utilization

93.4%

Of revised budget

Escalated

Cost Status

+11.1%

+₹200 Cr increase

Remaining

₹132 Cr

Budget left

Budget Utilization

93.4%
0%25%50%75%100%

Spent

₹1862 Cr

Remaining

₹132 Cr

Total

₹1994 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1794 Cr

Revised Cost

₹1994 Cr

Increase

+₹200 Cr

Escalation

+11.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

27/12/2025

Revised Completion

27/12/2025

Completed

Project Details

Project Code705454
SectorRailways
MinistryMinistry of Railways
StateMadhya Pradesh
Data Month2026-08

Financial Summary

Original Cost₹1794 Cr
Revised Cost₹1994 Cr
Expenditure₹1862 Cr
Original End Date27/12/2025
Revised Date27/12/2025

Project Intelligence

Cost has increased by ₹200 Cr (11.1%) from the original estimate of ₹1794 Cr.

Expenditure stands at ₹1862 Cr, which is 93.4% of the revised project cost.

Remaining budget: ₹132 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Chhota Udepur-Dhar 157 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1794.00 Cr, later revised to ₹1993.65 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Chhota Udepur-Dhar 157 km"?
Chhota Udepur-Dhar 157 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Madhya Pradesh. Original cost: ₹1794 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1794 Cr and has been revised to ₹1994 Cr — a cost overrun of +11.1%. Expenditure to date: ₹1862 Cr (93.4% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Chhota Udepur-Dhar 157 km is under the Ministry of Railways in the Railways sector. Project code: 705454. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Chhota Udepur-Dhar 157 km is one of several Bihar projects tracked under the Railways sector on the IPM system.