143.200 to km. 209.200
Original Cost
₹2128 Cr
Baseline estimate
Revised Cost
₹2172 Cr
Latest approved cost
Expenditure
₹98 Cr
Spent to date
Utilization
4.5%
Of revised cost
Cost Overrun
+2.0%
+₹44 Cr
Remaining
₹2074 Cr
Budget left
Spent
₹98 Cr
Remaining
₹2074 Cr
Total
₹2172 Cr
4.5%
Utilized
Original Cost
₹2128 Cr
Revised Cost
₹2172 Cr
Increase
+₹44 Cr
Escalation
+2.0%
Project Approved
Construction / Implementation
Original End Date
2013-07-24
Revised Completion
2026-04-30
Completed
Cost has increased by ₹44 Cr (2.0%) from the original estimate of ₹2128 Cr.
Expenditure stands at ₹98 Cr, which is 4.5% of the revised project cost.
Remaining budget: ₹2074 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.