Oil & GasIPM · Central Project#619196

Change of service of existing Mundra-Panipat Pipeline [Panipat - Churwa section] from Crude oil to Product

Ministry of Petroleum & Natural GasHaryana
Revised Cost: ₹359 CrUtilization: 16.2%

Original Cost

₹359 Cr

Baseline estimate

On budget

Revised Cost

₹359 Cr

Latest approved cost

Expenditure

₹58 Cr

Spent to date

Utilization

16.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹301 Cr

Budget left

Budget Utilization

16.2%
0%25%50%75%100%

Spent

₹58 Cr

Remaining

₹301 Cr

Total

₹359 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/04/2027

Revised Completion

30/04/2027

Completed

Project Details

Project Code619196
SectorOil & Gas
MinistryMinistry of Petroleum & Natural Gas
StateHaryana
Data Month2026-08

Financial Summary

Original Cost₹359 Cr
Revised Cost₹359 Cr
Expenditure₹58 Cr
Original End Date30/04/2027
Revised Date30/04/2027

Project Intelligence

Project is within original budget of ₹359 Cr — no cost escalation recorded.

Expenditure stands at ₹58 Cr, which is 16.2% of the revised project cost.

Remaining budget: ₹301 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.

Change of service of existing Mundra-Panipat Pipeline [Panipat - Churwa section] from Crude oil to Product is a centrally-funded infrastructure project under Ministry of Petroleum & Natural Gas, in the Oil & Gas sector. The original approved cost is ₹359.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Change of service of existing Mundra-Panipat Pipeline [Panipat - Churwa section]"?
Change of service of existing Mundra-Panipat Pipeline [Panipat - Churwa section] from Crude oil to Product is a centrally-funded infrastructure project under the Ministry of Petroleum & Natural Gas, tracked through the Investment Project Monitoring (IPM) system. Sector: Oil & Gas. State: Haryana. Original cost: ₹359 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹359 Cr has not been significantly revised. Expenditure: ₹58 Cr (16.2% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Change of service of existing Mundra-Panipat Pipeline [Panip is under the Ministry of Petroleum & Natural Gas in the Oil & Gas sector. Project code: 619196. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Change of service of existing Mundra-Panipat Pipeline [Panip is one of several Bihar projects tracked under the Oil & Gas sector on the IPM system.