Original Cost
₹8324 Cr
Baseline estimate
Revised Cost
₹8342 Cr
Latest approved cost
Expenditure
₹266 Cr
Spent to date
Utilization
3.2%
Of revised budget
Cost Status
+0.2%
+₹18 Cr increase
Remaining
₹8076 Cr
Budget left
Spent
₹266 Cr
Remaining
₹8076 Cr
Total
₹8342 Cr
Original Cost
₹8324 Cr
Revised Cost
₹8342 Cr
Increase
+₹18 Cr
Escalation
+0.2%
Project Approved
Construction / Implementation
Original End Date
31/03/2021
Revised Completion
31/03/2027
Completed
Cost has increased by ₹18 Cr (0.2%) from the original estimate of ₹8324 Cr.
Expenditure stands at ₹266 Cr, which is 3.2% of the revised project cost.
Remaining budget: ₹8076 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.