RailwaysIPM · Central Project +28.7% overrun#705567

Burhwal - Gonda - 3rd line 61.72 km

Ministry of RailwaysUttar Pradesh
Revised Cost: ₹1308 CrUtilization: 60.8%Overrun: +₹292 Cr

Original Cost

₹1016 Cr

Baseline estimate

+29% overrun

Revised Cost

₹1308 Cr

Latest approved cost

Expenditure

₹796 Cr

Spent to date

Utilization

60.8%

Of revised budget

Escalated

Cost Status

+28.7%

+₹292 Cr increase

Remaining

₹512 Cr

Budget left

Budget Utilization

60.8%
0%25%50%75%100%

Spent

₹796 Cr

Remaining

₹512 Cr

Total

₹1308 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1016 Cr

Revised Cost

₹1308 Cr

Increase

+₹292 Cr

Escalation

+28.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

25/03/2025

Revised Completion

30/05/2026

Completed

Project Details

Project Code705567
SectorRailways
MinistryMinistry of Railways
StateUttar Pradesh
Data Month2026-08

Financial Summary

Original Cost₹1016 Cr
Revised Cost₹1308 Cr
Expenditure₹796 Cr
Original End Date25/03/2025
Revised Date30/05/2026

Project Intelligence

Cost has increased by ₹292 Cr (28.7%) from the original estimate of ₹1016 Cr.

Expenditure stands at ₹796 Cr, which is 60.8% of the revised project cost.

Remaining budget: ₹512 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Burhwal - Gonda - 3rd line 61.72 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1016.00 Cr, later revised to ₹1307.62 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Burhwal - Gonda - 3rd line 61.72 km"?
Burhwal - Gonda - 3rd line 61.72 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Uttar Pradesh. Original cost: ₹1016 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1016 Cr and has been revised to ₹1308 Cr — a cost overrun of +28.7%. Expenditure to date: ₹796 Cr (60.8% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Burhwal - Gonda - 3rd line 61.72 km is under the Ministry of Railways in the Railways sector. Project code: 705567. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Burhwal - Gonda - 3rd line 61.72 km is one of several Bihar projects tracked under the Railways sector on the IPM system.