Burhwal - Gonda - 3rd line 61.72 km
Original Cost
₹1016 Cr
Baseline estimate
Revised Cost
₹1308 Cr
Latest approved cost
Expenditure
₹796 Cr
Spent to date
Utilization
60.8%
Of revised budget
Cost Status
+28.7%
+₹292 Cr increase
Remaining
₹512 Cr
Budget left
Budget Utilization
60.8%Spent
₹796 Cr
Remaining
₹512 Cr
Total
₹1308 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1016 Cr
Revised Cost
₹1308 Cr
Increase
+₹292 Cr
Escalation
+28.7%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
25/03/2025
Revised Completion
30/05/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹292 Cr (28.7%) from the original estimate of ₹1016 Cr.
Expenditure stands at ₹796 Cr, which is 60.8% of the revised project cost.
Remaining budget: ₹512 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Burhwal - Gonda - 3rd line 61.72 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1016.00 Cr, later revised to ₹1307.62 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Burhwal - Gonda - 3rd line 61.72 km"?
- Burhwal - Gonda - 3rd line 61.72 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Uttar Pradesh. Original cost: ₹1016 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1016 Cr and has been revised to ₹1308 Cr — a cost overrun of +28.7%. Expenditure to date: ₹796 Cr (60.8% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Burhwal - Gonda - 3rd line 61.72 km is under the Ministry of Railways in the Railways sector. Project code: 705567. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Burhwal - Gonda - 3rd line 61.72 km is one of several Bihar projects tracked under the Railways sector on the IPM system.