Original Cost
₹2083 Cr
Baseline estimate
Revised Cost
₹2860 Cr
Latest approved cost
Expenditure
₹730 Cr
Spent to date
Utilization
25.5%
Of revised budget
Cost Status
+37.3%
+₹777 Cr increase
Remaining
₹2129 Cr
Budget left
Spent
₹730 Cr
Remaining
₹2129 Cr
Total
₹2860 Cr
Original Cost
₹2083 Cr
Revised Cost
₹2860 Cr
Increase
+₹777 Cr
Escalation
+37.3%
Project Approved
Construction / Implementation
Original End Date
20/08/2019
Revised Completion
31/07/2026
Completed
Cost has increased by ₹777 Cr (37.3%) from the original estimate of ₹2083 Cr.
Expenditure stands at ₹730 Cr, which is 25.5% of the revised project cost.
Remaining budget: ₹2129 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.