Roads & HighwaysIPM · Central Project +37.3% overrun#619150

BRT Tiger Reserve Boundary Km.287.500 to Bangalore Section Km.458.420 of NH-209 in Karnataka

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹2860 CrUtilization: 78.4%Overrun: +₹777 Cr

Original Cost

₹2083 Cr

Baseline estimate

+37% overrun

Revised Cost

₹2860 Cr

Latest approved cost

Expenditure

₹2243 Cr

Spent to date

Utilization

78.4%

Of revised budget

Escalated

Cost Status

+37.3%

+₹777 Cr increase

Remaining

₹617 Cr

Budget left

Budget Utilization

78.4%
0%25%50%75%100%

Spent

₹2243 Cr

Remaining

₹617 Cr

Total

₹2860 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2083 Cr

Revised Cost

₹2860 Cr

Increase

+₹777 Cr

Escalation

+37.3%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

20/08/2019

Revised Completion

30/09/2026

Completed

Project Details

Project Code619150
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹2083 Cr
Revised Cost₹2860 Cr
Expenditure₹2243 Cr
Original End Date20/08/2019
Revised Date30/09/2026

Project Intelligence

Cost has increased by ₹777 Cr (37.3%) from the original estimate of ₹2083 Cr.

Expenditure stands at ₹2243 Cr, which is 78.4% of the revised project cost.

Remaining budget: ₹617 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

BRT Tiger Reserve Boundary Km.287.500 to Bangalore Section Km.458.420 of NH-209 in Karnataka is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2083.00 Cr, later revised to ₹2859.93 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "BRT Tiger Reserve Boundary Km.287.500 to Bangalore Section Km.458.420 of NH-209 "?
BRT Tiger Reserve Boundary Km.287.500 to Bangalore Section Km.458.420 of NH-209 in Karnataka is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹2083 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2083 Cr and has been revised to ₹2860 Cr — a cost overrun of +37.3%. Expenditure to date: ₹2243 Cr (78.4% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
BRT Tiger Reserve Boundary Km.287.500 to Bangalore Section K is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619150. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. BRT Tiger Reserve Boundary Km.287.500 to Bangalore Section K is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.