BRT Tiger Reserve Boundary Km.287.500 to Bangalore Section Km.458.420 of NH-209 in Karnataka
Original Cost
₹2083 Cr
Baseline estimate
Revised Cost
₹2860 Cr
Latest approved cost
Expenditure
₹2243 Cr
Spent to date
Utilization
78.4%
Of revised budget
Cost Status
+37.3%
+₹777 Cr increase
Remaining
₹617 Cr
Budget left
Budget Utilization
78.4%Spent
₹2243 Cr
Remaining
₹617 Cr
Total
₹2860 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹2083 Cr
Revised Cost
₹2860 Cr
Increase
+₹777 Cr
Escalation
+37.3%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
20/08/2019
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹777 Cr (37.3%) from the original estimate of ₹2083 Cr.
Expenditure stands at ₹2243 Cr, which is 78.4% of the revised project cost.
Remaining budget: ₹617 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
BRT Tiger Reserve Boundary Km.287.500 to Bangalore Section Km.458.420 of NH-209 in Karnataka is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2083.00 Cr, later revised to ₹2859.93 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "BRT Tiger Reserve Boundary Km.287.500 to Bangalore Section Km.458.420 of NH-209 "?
- BRT Tiger Reserve Boundary Km.287.500 to Bangalore Section Km.458.420 of NH-209 in Karnataka is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹2083 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹2083 Cr and has been revised to ₹2860 Cr — a cost overrun of +37.3%. Expenditure to date: ₹2243 Cr (78.4% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- BRT Tiger Reserve Boundary Km.287.500 to Bangalore Section K is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619150. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. BRT Tiger Reserve Boundary Km.287.500 to Bangalore Section K is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.