RailwaysIPM · Central Project +14.6% overrun#706854

Boridand-Ambikapur 118.81 km Umbrella work PB57/2019-20/NR

Ministry of RailwaysChhattisgarh
Revised Cost: ₹1577 CrUtilization: 32.5%Overrun: +₹201 Cr

Original Cost

₹1376 Cr

Baseline estimate

+15% overrun

Revised Cost

₹1577 Cr

Latest approved cost

Expenditure

₹512 Cr

Spent to date

Utilization

32.5%

Of revised budget

Escalated

Cost Status

+14.6%

+₹201 Cr increase

Remaining

₹1065 Cr

Budget left

Budget Utilization

32.5%
0%25%50%75%100%

Spent

₹512 Cr

Remaining

₹1065 Cr

Total

₹1577 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1376 Cr

Revised Cost

₹1577 Cr

Increase

+₹201 Cr

Escalation

+14.6%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/06/2030

Revised Completion

30/06/2030

Completed

Project Details

Project Code706854
SectorRailways
MinistryMinistry of Railways
StateChhattisgarh
Data Month2026-08

Financial Summary

Original Cost₹1376 Cr
Revised Cost₹1577 Cr
Expenditure₹512 Cr
Original End Date30/06/2030
Revised Date30/06/2030

Project Intelligence

Cost has increased by ₹201 Cr (14.6%) from the original estimate of ₹1376 Cr.

Expenditure stands at ₹512 Cr, which is 32.5% of the revised project cost.

Remaining budget: ₹1065 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Boridand-Ambikapur 118.81 km Umbrella work PB57/2019-20/NR is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1376.00 Cr, later revised to ₹1576.72 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Boridand-Ambikapur 118.81 km Umbrella work PB57/2019-20/NR"?
Boridand-Ambikapur 118.81 km Umbrella work PB57/2019-20/NR is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Chhattisgarh. Original cost: ₹1376 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1376 Cr and has been revised to ₹1577 Cr — a cost overrun of +14.6%. Expenditure to date: ₹512 Cr (32.5% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Boridand-Ambikapur 118.81 km Umbrella work PB57/2019-20/NR is under the Ministry of Railways in the Railways sector. Project code: 706854. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Boridand-Ambikapur 118.81 km Umbrella work PB57/2019-20/NR is one of several Bihar projects tracked under the Railways sector on the IPM system.