Water ResourcesIPM · Central Project#617422

Bodwad Parisar Sinchan Yojna

Department of Water Resources, River Development & GRMaharashtra
Revised Cost: ₹1924 CrUtilization: 17.6%

Original Cost

₹1924 Cr

Baseline estimate

On budget

Revised Cost

₹1924 Cr

Latest approved cost

Expenditure

₹339 Cr

Spent to date

Utilization

17.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1585 Cr

Budget left

Budget Utilization

17.6%
0%25%50%75%100%

Spent

₹339 Cr

Remaining

₹1585 Cr

Total

₹1924 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/07/2027

Revised Completion

Completed

Project Details

Project Code617422
SectorWater Resources
MinistryDepartment of Water Resources, River Development & GR
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹1924 Cr
Revised Cost₹1924 Cr
Expenditure₹339 Cr
Original End Date31/07/2027
Revised DateN/A

Project Intelligence

Project is within original budget of ₹1924 Cr — no cost escalation recorded.

Expenditure stands at ₹339 Cr, which is 17.6% of the revised project cost.

Remaining budget: ₹1585 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.

Bodwad Parisar Sinchan Yojna is a centrally-funded infrastructure project under Department of Water Resources, River Development & GR, in the Water Resources sector. The original approved cost is ₹1924.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Bodwad Parisar Sinchan Yojna"?
Bodwad Parisar Sinchan Yojna is a centrally-funded infrastructure project under the Department of Water Resources, River Development & GR, tracked through the Investment Project Monitoring (IPM) system. Sector: Water Resources. State: Maharashtra. Original cost: ₹1924 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹1924 Cr has not been significantly revised. Expenditure: ₹339 Cr (17.6% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Bodwad Parisar Sinchan Yojna is under the Department of Water Resources, River Development & GR in the Water Resources sector. Project code: 617422. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Bodwad Parisar Sinchan Yojna is one of several Bihar projects tracked under the Water Resources sector on the IPM system.