Roads & HighwaysIPM · Central Project#618572

Binnaguri Bypass-Descoped portion of Ghoshpukur-Dhupguri Section of NH-31Dpkg-1

Ministry of Road Transport & HighwaysWest Bengal
Revised Cost: ₹306 CrUtilization: 1.6%

Original Cost

₹310 Cr

Baseline estimate

On budget

Revised Cost

₹306 Cr

Latest approved cost

Expenditure

₹5 Cr

Spent to date

Utilization

1.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹301 Cr

Budget left

Budget Utilization

1.6%
0%25%50%75%100%

Spent

₹5 Cr

Remaining

₹301 Cr

Total

₹306 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

06/11/2027

Revised Completion

06/11/2027

Completed

Project Details

Project Code618572
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateWest Bengal
Data Month2026-08

Financial Summary

Original Cost₹310 Cr
Revised Cost₹306 Cr
Expenditure₹5 Cr
Original End Date06/11/2027
Revised Date06/11/2027

Project Intelligence

Project is within original budget of ₹310 Cr — no cost escalation recorded.

Expenditure stands at ₹5 Cr, which is 1.6% of the revised project cost.

Remaining budget: ₹301 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Binnaguri Bypass-Descoped portion of Ghoshpukur-Dhupguri Section of NH-31Dpkg-1 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹310.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Binnaguri Bypass-Descoped portion of Ghoshpukur-Dhupguri Section of NH-31Dpkg-1"?
Binnaguri Bypass-Descoped portion of Ghoshpukur-Dhupguri Section of NH-31Dpkg-1 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: West Bengal. Original cost: ₹310 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹310 Cr and has been revised to ₹306 Cr — a cost overrun of -1.3%. Expenditure to date: ₹5 Cr (1.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Binnaguri Bypass-Descoped portion of Ghoshpukur-Dhupguri Sec is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618572. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Binnaguri Bypass-Descoped portion of Ghoshpukur-Dhupguri Sec is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.