Original Cost
₹1353 Cr
Baseline estimate
Revised Cost
₹2685 Cr
Latest approved cost
Expenditure
₹2690 Cr
Spent to date
Utilization
100.2%
Of revised budget
Cost Status
+98.5%
+₹1332 Cr increase
Remaining
₹0 Cr
Budget left
Spent
₹2690 Cr
Remaining
₹0 Cr
Total
₹2685 Cr
Original Cost
₹1353 Cr
Revised Cost
₹2685 Cr
Increase
+₹1332 Cr
Escalation
+98.5%
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
30/06/2025
Completed
Cost has increased by ₹1332 Cr (98.5%) from the original estimate of ₹1353 Cr.
Expenditure stands at ₹2690 Cr, which is 100.2% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.