Original Cost
₹1560 Cr
Baseline estimate
Revised Cost
₹1568 Cr
Latest approved cost
Expenditure
₹92 Cr
Spent to date
Utilization
5.8%
Of revised budget
Cost Status
+0.5%
+₹8 Cr increase
Remaining
₹1477 Cr
Budget left
Spent
₹92 Cr
Remaining
₹1477 Cr
Total
₹1568 Cr
Original Cost
₹1560 Cr
Revised Cost
₹1568 Cr
Increase
+₹8 Cr
Escalation
+0.5%
Project Approved
Construction / Implementation
Original End Date
26/09/2016
Revised Completion
31/08/2026
Completed
Cost has increased by ₹8 Cr (0.5%) from the original estimate of ₹1560 Cr.
Expenditure stands at ₹92 Cr, which is 5.8% of the revised project cost.
Remaining budget: ₹1477 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.