Original Cost
₹2298 Cr
Baseline estimate
Revised Cost
₹2734 Cr
Latest approved cost
Expenditure
₹430 Cr
Spent to date
Utilization
15.7%
Of revised budget
Cost Status
+19.0%
+₹436 Cr increase
Remaining
₹2304 Cr
Budget left
Spent
₹430 Cr
Remaining
₹2304 Cr
Total
₹2734 Cr
Original Cost
₹2298 Cr
Revised Cost
₹2734 Cr
Increase
+₹436 Cr
Escalation
+19.0%
Project Approved
Construction / Implementation
Original End Date
31/12/2026
Revised Completion
31/12/2030
Completed
Cost has increased by ₹436 Cr (19.0%) from the original estimate of ₹2298 Cr.
Expenditure stands at ₹430 Cr, which is 15.7% of the revised project cost.
Remaining budget: ₹2304 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.