Barabanki-Malhaur - 3rd & 4th Line 32.84 km
Original Cost
₹407 Cr
Baseline estimate
Revised Cost
₹480 Cr
Latest approved cost
Expenditure
₹445 Cr
Spent to date
Utilization
92.7%
Of revised budget
Cost Status
+18.0%
+₹73 Cr increase
Remaining
₹35 Cr
Budget left
Budget Utilization
92.7%Spent
₹445 Cr
Remaining
₹35 Cr
Total
₹480 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹407 Cr
Revised Cost
₹480 Cr
Increase
+₹73 Cr
Escalation
+18.0%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/03/2025
Revised Completion
31/08/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹73 Cr (18.0%) from the original estimate of ₹407 Cr.
Expenditure stands at ₹445 Cr, which is 92.7% of the revised project cost.
Remaining budget: ₹35 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Barabanki-Malhaur - 3rd & 4th Line 32.84 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹407.00 Cr, later revised to ₹480.13 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Barabanki-Malhaur - 3rd & 4th Line 32.84 km"?
- Barabanki-Malhaur - 3rd & 4th Line 32.84 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Uttar Pradesh. Original cost: ₹407 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹407 Cr and has been revised to ₹480 Cr — a cost overrun of +18%. Expenditure to date: ₹445 Cr (92.7% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Barabanki-Malhaur - 3rd & 4th Line 32.84 km is under the Ministry of Railways in the Railways sector. Project code: 705782. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Barabanki-Malhaur - 3rd & 4th Line 32.84 km is one of several Bihar projects tracked under the Railways sector on the IPM system.