Original Cost
₹15.8K Cr
Baseline estimate
Revised Cost
₹15.8K Cr
Latest approved cost
Expenditure
₹3278 Cr
Spent to date
Utilization
20.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹12.5K Cr
Budget left
Spent
₹3278 Cr
Remaining
₹12.5K Cr
Total
₹15.8K Cr
Project Approved
Construction / Implementation
Original End Date
31/12/2026
Revised Completion
31/03/2030
Completed
Mega infrastructure project worth ₹15.8K Cr — among the largest central projects in Karnataka.
Project is within original budget of ₹15.8K Cr — no cost escalation recorded.
Expenditure stands at ₹3278 Cr, which is 20.8% of the revised project cost.
Remaining budget: ₹12.5K Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.