Balance works of four lane from km 43.950 Thiruvallur Bypass to km 61.470 Veppampattu Bypass passing through Thannerkulam, Thozur and Sevapet Bypass 17.520 kms of Tirupathi- Tiruttani- Chennai section of NH 205
Original Cost
₹468 Cr
Baseline estimate
Revised Cost
₹700 Cr
Latest approved cost
Expenditure
₹596 Cr
Spent to date
Utilization
85.2%
Of revised budget
Cost Status
+49.5%
+₹232 Cr increase
Remaining
₹104 Cr
Budget left
Budget Utilization
85.2%Spent
₹596 Cr
Remaining
₹104 Cr
Total
₹700 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹468 Cr
Revised Cost
₹700 Cr
Increase
+₹232 Cr
Escalation
+49.5%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
20/09/2024
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹232 Cr (49.5%) from the original estimate of ₹468 Cr.
Expenditure stands at ₹596 Cr, which is 85.2% of the revised project cost.
Remaining budget: ₹104 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Balance works of four lane from km 43.950 Thiruvallur Bypass to km 61.470 Veppampattu Bypass passing through Thannerkulam, Thozur and Sevapet Bypass 17.520 kms of Tirupathi- Tiruttani- Chennai section of NH 205 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹468.00 Cr, later revised to ₹699.68 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Balance works of four lane from km 43.950 Thiruvallur Bypass to km 61.470 Veppam"?
- Balance works of four lane from km 43.950 Thiruvallur Bypass to km 61.470 Veppampattu Bypass passing through Thannerkulam, Thozur and Sevapet Bypass 17.520 kms of Tirupathi- Tiruttani- Chennai section of NH 205 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tamil Nadu. Original cost: ₹468 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹468 Cr and has been revised to ₹700 Cr — a cost overrun of +49.5%. Expenditure to date: ₹596 Cr (85.2% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Balance works of four lane from km 43.950 Thiruvallur Bypass is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619222. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Balance works of four lane from km 43.950 Thiruvallur Bypass is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.