Roads & HighwaysIPM · Central Project +49.5% overrun#619222

Balance works of four lane from km 43.950 Thiruvallur Bypass to km 61.470 Veppampattu Bypass passing through Thannerkulam, Thozur and Sevapet Bypass 17.520 kms of Tirupathi- Tiruttani- Chennai section of NH 205

Ministry of Road Transport & HighwaysTamil Nadu
Revised Cost: ₹700 CrUtilization: 85.2%Overrun: +₹232 Cr

Original Cost

₹468 Cr

Baseline estimate

+50% overrun

Revised Cost

₹700 Cr

Latest approved cost

Expenditure

₹596 Cr

Spent to date

Utilization

85.2%

Of revised budget

Escalated

Cost Status

+49.5%

+₹232 Cr increase

Remaining

₹104 Cr

Budget left

Budget Utilization

85.2%
0%25%50%75%100%

Spent

₹596 Cr

Remaining

₹104 Cr

Total

₹700 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹468 Cr

Revised Cost

₹700 Cr

Increase

+₹232 Cr

Escalation

+49.5%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

20/09/2024

Revised Completion

30/09/2026

Completed

Project Details

Project Code619222
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateTamil Nadu
Data Month2026-08

Financial Summary

Original Cost₹468 Cr
Revised Cost₹700 Cr
Expenditure₹596 Cr
Original End Date20/09/2024
Revised Date30/09/2026

Project Intelligence

Cost has increased by ₹232 Cr (49.5%) from the original estimate of ₹468 Cr.

Expenditure stands at ₹596 Cr, which is 85.2% of the revised project cost.

Remaining budget: ₹104 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Balance works of four lane from km 43.950 Thiruvallur Bypass to km 61.470 Veppampattu Bypass passing through Thannerkulam, Thozur and Sevapet Bypass 17.520 kms of Tirupathi- Tiruttani- Chennai section of NH 205 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹468.00 Cr, later revised to ₹699.68 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Balance works of four lane from km 43.950 Thiruvallur Bypass to km 61.470 Veppam"?
Balance works of four lane from km 43.950 Thiruvallur Bypass to km 61.470 Veppampattu Bypass passing through Thannerkulam, Thozur and Sevapet Bypass 17.520 kms of Tirupathi- Tiruttani- Chennai section of NH 205 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tamil Nadu. Original cost: ₹468 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹468 Cr and has been revised to ₹700 Cr — a cost overrun of +49.5%. Expenditure to date: ₹596 Cr (85.2% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Balance works of four lane from km 43.950 Thiruvallur Bypass is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619222. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Balance works of four lane from km 43.950 Thiruvallur Bypass is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.