Original Cost
₹468 Cr
Baseline estimate
Revised Cost
₹700 Cr
Latest approved cost
Expenditure
₹451 Cr
Spent to date
Utilization
64.5%
Of revised budget
Cost Status
+49.5%
+₹232 Cr increase
Remaining
₹248 Cr
Budget left
Spent
₹451 Cr
Remaining
₹248 Cr
Total
₹700 Cr
Original Cost
₹468 Cr
Revised Cost
₹700 Cr
Increase
+₹232 Cr
Escalation
+49.5%
Project Approved
Construction / Implementation
Original End Date
20/09/2024
Revised Completion
20/06/2026
Completed
Cost has increased by ₹232 Cr (49.5%) from the original estimate of ₹468 Cr.
Expenditure stands at ₹451 Cr, which is 64.5% of the revised project cost.
Remaining budget: ₹248 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.