to Km 440.00 Devanpur - Kotwa
Original Cost
₹210 Cr
Baseline estimate
Revised Cost
₹358 Cr
Latest approved cost
Expenditure
₹116 Cr
Spent to date
Utilization
32.5%
Of revised cost
Cost Overrun
+70.6%
+₹148 Cr
Remaining
₹242 Cr
Budget left
Spent
₹116 Cr
Remaining
₹242 Cr
Total
₹358 Cr
32.5%
Utilized
Original Cost
₹210 Cr
Revised Cost
₹358 Cr
Increase
+₹148 Cr
Escalation
+70.6%
Project Approved
Construction / Implementation
Original End Date
2024-01-30
Revised Completion
2026-12-31
Completed
Cost has increased by ₹148 Cr (70.6%) from the original estimate of ₹210 Cr.
Expenditure stands at ₹116 Cr, which is 32.5% of the revised project cost.
Remaining budget: ₹242 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.