Roads & HighwaysIPM · Central Project +70.6% overrun#618569

Balance work - WB-10 Gandak Bridge Km 402.00 to Km 440.00 Devanpur - Kotwa

Ministry of Road Transport & HighwaysBihar
Revised Cost: ₹358 CrUtilization: 50.8%Overrun: +₹148 Cr

Original Cost

₹210 Cr

Baseline estimate

+71% overrun

Revised Cost

₹358 Cr

Latest approved cost

Expenditure

₹182 Cr

Spent to date

Utilization

50.8%

Of revised budget

Escalated

Cost Status

+70.6%

+₹148 Cr increase

Remaining

₹176 Cr

Budget left

Budget Utilization

50.8%
0%25%50%75%100%

Spent

₹182 Cr

Remaining

₹176 Cr

Total

₹358 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹210 Cr

Revised Cost

₹358 Cr

Increase

+₹148 Cr

Escalation

+70.6%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/01/2024

Revised Completion

28/02/2027

Completed

Project Details

Project Code618569
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateBihar
Data Month2026-06

Financial Summary

Original Cost₹210 Cr
Revised Cost₹358 Cr
Expenditure₹182 Cr
Original End Date30/01/2024
Revised Date28/02/2027

Project Intelligence

Cost has increased by ₹148 Cr (70.6%) from the original estimate of ₹210 Cr.

Expenditure stands at ₹182 Cr, which is 50.8% of the revised project cost.

Remaining budget: ₹176 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Balance work - WB-10 Gandak Bridge Km 402.00 to Km 440.00 Devanpur - Kotwa is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹210.00 Cr, later revised to ₹358.30 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Balance work - WB-10 Gandak Bridge Km 402.00 to Km 440.00 Devanpur - Kotwa"?
Balance work - WB-10 Gandak Bridge Km 402.00 to Km 440.00 Devanpur - Kotwa is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹210 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹210 Cr and has been revised to ₹358 Cr — a cost overrun of +70.6%. Expenditure to date: ₹182 Cr (50.8% of revised cost). Data as of 2026-06.
QWhich ministry is responsible for this project?
Balance work - WB-10 Gandak Bridge Km 402.00 to Km 440.00 De is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618569. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Balance work - WB-10 Gandak Bridge Km 402.00 to Km 440.00 De is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.