Original Cost
₹278 Cr
Baseline estimate
Revised Cost
₹278 Cr
Latest approved cost
Expenditure
₹40 Cr
Spent to date
Utilization
14.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹238 Cr
Budget left
Spent
₹40 Cr
Remaining
₹238 Cr
Total
₹278 Cr
Project Approved
Construction / Implementation
Original End Date
27/12/2026
Revised Completion
27/12/2026
Completed
Project is within original budget of ₹278 Cr — no cost escalation recorded.
Expenditure stands at ₹40 Cr, which is 14.5% of the revised project cost.
Remaining budget: ₹238 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.