Roads & HighwaysIPM · Central Project#618198

Balance work of Rehabilitation and Up-gradation to 2-lane road with paved shoulders configuration for NH- 965DD from Pacharal-Mandangad-Mhapral-Rajewadi Upto Junction of NH-66 Ch-22700 to 75100 Km and Ambadave connector Birth place of Dr. Babasaheb Ambedkar Ch-0000 to 7325 Km length Km 59.725 in the state of Maharashtra on EPC mode. Balance Work

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹342 CrUtilization: 73.1%

Original Cost

₹389 Cr

Baseline estimate

On budget

Revised Cost

₹342 Cr

Latest approved cost

Expenditure

₹250 Cr

Spent to date

Utilization

73.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹92 Cr

Budget left

Budget Utilization

73.1%
0%25%50%75%100%

Spent

₹250 Cr

Remaining

₹92 Cr

Total

₹342 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

04/01/2024

Revised Completion

31/10/2026

Completed

Project Details

Project Code618198
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹389 Cr
Revised Cost₹342 Cr
Expenditure₹250 Cr
Original End Date04/01/2024
Revised Date31/10/2026

Project Intelligence

Project is within original budget of ₹389 Cr — no cost escalation recorded.

Expenditure stands at ₹250 Cr, which is 73.1% of the revised project cost.

Remaining budget: ₹92 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Balance work of Rehabilitation and Up-gradation to 2-lane road with paved shoulders configuration for NH- 965DD from Pacharal-Mandangad-Mhapral-Rajewadi Upto Junction of NH-66 Ch-22700 to 75100 Km and Ambadave connector Birth place of Dr. Babasaheb Ambedkar Ch-0000 to 7325 Km length Km 59.725 in the state of Maharashtra on EPC mode. Balance Work is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹389.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Balance work of Rehabilitation and Up-gradation to 2-lane road with paved should"?
Balance work of Rehabilitation and Up-gradation to 2-lane road with paved shoulders configuration for NH- 965DD from Pacharal-Mandangad-Mhapral-Rajewadi Upto Junction of NH-66 Ch-22700 to 75100 Km and Ambadave connector Birth place of Dr. Babasaheb Ambedkar Ch-0000 to 7325 Km length Km 59.725 in the state of Maharashtra on EPC mode. Balance Work is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹389 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹389 Cr and has been revised to ₹342 Cr — a cost overrun of -12.2%. Expenditure to date: ₹250 Cr (73.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Balance work of Rehabilitation and Up-gradation to 2-lane ro is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618198. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Balance work of Rehabilitation and Up-gradation to 2-lane ro is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.