Balance work of Construction of Two/Four lane with paved shoulder from Km 422.000 to 523.600 Chitradurga to Shivamogga of NH-13 in the state of Kanataka on EPC mode.
Original Cost
₹517 Cr
Baseline estimate
Revised Cost
₹517 Cr
Latest approved cost
Expenditure
₹387 Cr
Spent to date
Utilization
74.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹131 Cr
Budget left
Budget Utilization
74.8%Spent
₹387 Cr
Remaining
₹131 Cr
Total
₹517 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/12/2025
Revised Completion
30/08/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹517 Cr — no cost escalation recorded.
Expenditure stands at ₹387 Cr, which is 74.8% of the revised project cost.
Remaining budget: ₹131 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Balance work of Construction of Two/Four lane with paved shoulder from Km 422.000 to 523.600 Chitradurga to Shivamogga of NH-13 in the state of Kanataka on EPC mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹517.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Balance work of Construction of Two/Four lane with paved shoulder from Km 422.00"?
- Balance work of Construction of Two/Four lane with paved shoulder from Km 422.000 to 523.600 Chitradurga to Shivamogga of NH-13 in the state of Kanataka on EPC mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹517 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹517 Cr has not been significantly revised. Expenditure: ₹387 Cr (74.8% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Balance work of Construction of Two/Four lane with paved sho is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618031. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Balance work of Construction of Two/Four lane with paved sho is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.