Roads & HighwaysIPM · Central Project#618031

Balance work of Construction of Two/Four lane with paved shoulder from Km 422.000 to 523.600 Chitradurga to Shivamogga of NH-13 in the state of Kanataka on EPC mode.

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹517 CrUtilization: 74.8%

Original Cost

₹517 Cr

Baseline estimate

On budget

Revised Cost

₹517 Cr

Latest approved cost

Expenditure

₹387 Cr

Spent to date

Utilization

74.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹131 Cr

Budget left

Budget Utilization

74.8%
0%25%50%75%100%

Spent

₹387 Cr

Remaining

₹131 Cr

Total

₹517 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/12/2025

Revised Completion

30/08/2026

Completed

Project Details

Project Code618031
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹517 Cr
Revised Cost₹517 Cr
Expenditure₹387 Cr
Original End Date30/12/2025
Revised Date30/08/2026

Project Intelligence

Project is within original budget of ₹517 Cr — no cost escalation recorded.

Expenditure stands at ₹387 Cr, which is 74.8% of the revised project cost.

Remaining budget: ₹131 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Balance work of Construction of Two/Four lane with paved shoulder from Km 422.000 to 523.600 Chitradurga to Shivamogga of NH-13 in the state of Kanataka on EPC mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹517.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Balance work of Construction of Two/Four lane with paved shoulder from Km 422.00"?
Balance work of Construction of Two/Four lane with paved shoulder from Km 422.000 to 523.600 Chitradurga to Shivamogga of NH-13 in the state of Kanataka on EPC mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹517 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹517 Cr has not been significantly revised. Expenditure: ₹387 Cr (74.8% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Balance work of Construction of Two/Four lane with paved sho is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618031. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Balance work of Construction of Two/Four lane with paved sho is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.